VDOT Updates Greene Supervisors

By Brent Wilson, Field Officer

Normally,  Virginia Department of Transportation (VDOT)  Residency Administrator Joel imageDenunzio provides the Greene County Board of Supervisors update.  In the October 9th meeting, Deputy Administrator Ed Nicholas filled in for Denunzio to give the  report.

Nicholas indicated the recent flooding events, especially in Madison and Stanardsville, have been a challenge to address across the district and that also delayed the normal mowing schedule.  He also addressed specific problems starting with South River on either side of Route 230 (Wolftown Road). In order to redirect the river on the west side of Route 230 back to where it had previously flowed, they are working with the property owner to develop a solution.  Once the solution has been fully engineered, an environmental permit will be required before they, or the property owner, can commence with this work.

image
South River Road

Prior to the Nicholas’ presentation, a young man and his mother spoke during ‘Matters From The Public’ and the youth addressed the South River Road flooding and its impacts on his life.  Chair Michelle Flynn (Ruckersville) asked Nicholas if VDOT could try to contact the young man and show he and his mother what is planned.

Also to be accomplished this week is to work on final grading and seeding on Route 33 near the Shenandoah National Park. In addition, in the next two weeks the VDOT property at the intersection of Route 33 and the Route 33 bypass will be cleared of debris, have dirt spread and it will be reseeded.

Supervisor Bill Martin (Stanardsville) mentioned to Nicholas that Greene County is reaching out to Washington, Richmond and the Army Corps of Engineers to ask for guidance/help on how to go forward with modifying the flow of several rivers in the county to minimize the impact to roadways. Martin asked that VDOT participate in these discussions.

Supervisor David Cox (Monroe) asked Nicholas what the priorities were on paving/patching the secondary roads in the county that have not yet been completed due to flooding. Especially Route 674 – Parker Mountain Road which is a 2 mile long stretch has a great many potholes and it needs to be addressed.  Nicholas assured Cox that VDOT would address this road and any roadway that is a safety issue.

Flynn brought up the final issue for VDOT asking when will Preddy Creek Road going away from Sheetz be addressed? The roadway continues to degrade and patching doesn’t seem to resolve the problem. Nicholas indicated that he would research the problem and reply with a timetable to address the issue.

Brent Wilson is the Greene County Field Officer for the Free Enterprise Forum a privately funded public policy organization.  The Free Enterprise Forum Field Officer program is funded by a generous grant from the Charlottesville Area Association of REALTORS® (CAAR) and by readers like you.  To support this important work please donate online at http://www.freeenterpriseforum.org

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s